Flood Situations Update

 
 

January 5, 2012

Subject: Building a dike in Rojana Industrial Park Ayutthaya
To: Whom it may concern

For preventing any further damages which may caused by flooding in the future, Rojana Industrial Park has hired the engineer team to design a dike, which the construction will be finished in September 2012 (approximately).

Thus, we will hold a conference to inform our value customers by this month. Date, Time and Place will be announced later on.


Faithfully yours,

ROJANA INDUSTRIAL PARK COMPANY LIMITED

 

December 27, 2011

To: Whom It May Concern

Due to the long holidays for an upcoming new year 2012. Rojana Industrial Park would like to inform you the telephone numbers of involved department which will be handled with any emergency case also safety standard as per the details attached.


Faithfully yours,

ROJANA INDUSTRIAL PARK PLC

 

December 23, 2011

To: Whom It May Concern

The Office of Insurance Commission has arranged a Meeting to report on the progress on assistance and flood alleviation on Wednesday, December 28, 2011.

They would like hereby to invite all entrepreneurs to participate in this meeting as per the details attached.


Faithfully yours,

ROJANA INDUSTRIAL PARK PLC

 

December 21, 2011

To: Whom It May Concern

Please be informed that Ayuthaya Provincial Industry Office has arranged a Meeting with all entrepreneurs who have been affected and damaged by the flooding in Rojana Industrial Park on Monday, December 26, 2011, at 14.00 hrs. at the Meeting Room 1, 3rd Floor, Ayutthaya City Hall. The meeting is to clarify and make suggestions on the factory rehabilitation after the flooding as per the details attached.


Faithfully yours,

ROJANA INDUSTRIAL PARK PLC

 

December 21, 2011

Re: Postponement of the Meeting on “Water Management Strategies”
To: Whom It May Concern

Please be informed that the Meeting on “Water Management Strategies in Seven Industrial Estates”, which is organized by Export Promotion Department on December 26, 2011, during 09.00 – 15.30 hrs. at Siam Niramitr, has been postponed as per the details attached.


Faithfully yours,

ROJANA INDUSTRIAL PARK PLC

 

November 28, 2011

To whom it may concern

Please kindly be informed for Waste Management as follows;

  • General Waste : Contact Rojana Industrial Park Office at Ayutthaya (Khun Sunanta and Khun Aree)
  • Industrial Waste : Contact company that is licensed by the Department of Industrial Works
  • Sewage : Please operate within December 2011

For more information, Please contact tel.no 0 3533 0000-2


Faithfully yours,

ROJANA INDUSTRIAL PARK COMPANY LIMITED

 

November 26, 2011

To whom it may concern

Ayutthaya Provincial Industrial would like to be informed about movement of product, material or machine from flood affected businesses for temporary storag, maintenance or production.

Ayutthaya Provincial Industrial Office will consider assistance for allocation of building etc.

Please see file attached for detail Download


Faithfully yours,

ROJANA INDUSTRIAL PARK PUBLIC COMPANY LIMITED

 

November 14, 2011

To whom it may concern

Please be informed that from November 16, 2011 onwards, the Provincial Electricity Authority, Ayutthaya will open its temporary office at Rojana Industrial Park’s office. This is for convenience of the customers located in Rojana Industrial Park (Ayutthaya) in coordinating with the PEA Ayutthaya

However, in the event where any customer finds it inconvenient to go to Ayutthaya, the coordination with the PEA Ayutthaya can be made by phone with the following contact persons and telephone numbers.

1. Khun Kampol Phone No. 086-6264758
2. Khun Sanya Phone No. 089-7983220


Faithfully yours,

ROJANA INDUSTRIAL PARK PUBLIC COMPANY LIMITED

 

10-Nov-11
Rojana Industrial Park

PEA (380V)temporary power supply until 22kv line recover

Power supply is usually being done with 22kv line by PEA or Rojana Power. However, it will take around 1 month to recover 22kv line. Therefore PEA is now considering that they will supply 380V power supply temporarily for cleaning of factory and light in factory.

This service can be applied by not only PEA customers but also Rojana Power customers. Basically, 380V line(already installerd for lighting road inside of Rojana Industrial Park) does not have enough capacity.
Therefore the supply capacity shall be limeited within 30kw for each customer.
Anyway please contact following PEA staff directly for detailed information.

Please see file attached for detail. Download

PEA Ayuttaya / Mr.Sanya Phongamphai
Mobile Phone 089-798-3220

 

Dear Investors,

Rojana Industrial park co.,ltd. herein declared our plan to operate dewatering from the park: The schedule of operation as follows:

1. ROJANA 3 (Phase 8) Start from 7 November 2011
2. ROJANA 1-2 (Phase 1-7) Start from 10-11 November 2011

 

27th October 2011

The declaration on the relief policy of ROJANA industrial park from flooded.

Dear Sir,

In consideration of ROJANA has the intention to announce the policy on flood relief and our current situation by given details as followed:

Date: Monday 31 October 2011

Time: 10.00 A.M.- 12.00 A.M. (Morning Session)

Venue: Jasmine City Hotel, L floor (Royal Jasmine room)

Whom who wish to attend the meeting please kindly register at ROJANA office within 28th October 2011 by calling Kn. Anucha at these following numbers 02-2592400-3 or 081-3757-002

Note: Due to the seats are limited, ROJANA shall limit the attendee for each company at 2 persons.


For your consideration

Faithfully yours,

Mr. Witaya Launglueyos

Senior General Manager

 

Permission to allow the safeguards operate for each factory.

  1. The company must inform to Rojana by mentioning Date and time ( During daytime or whole day) Name-Surname and id number of each safeguard who will be on duty.
  2. The safeguards must arrange vehicle and others necessity by their own such as Boat, food etc.
  3. The company must send the original copy of permission said above to ROJANA head office in BKK OR declare at Rojana office in Ayutthaya prior to their entrance.
  4. Before entering to the area the safeguards team must declare themselves, together with the copy of their ID card at ROJANA office in Ayutthaya, ROJANA 1 gate A

For more information kindly contact.

Rojana Bangkok

Kindly Contact: Khun: Anucha Ext 132, Khun Siriporn Ext 133

Rojana Ayutthaya

Kindly Contact: 080-018-3781, 080-018-2174

Or simply log on to our website: www.rojana.com

 

Permission to enter the factory area :

  • Letter from the company :
    1. have to specific name and surname with mobile no. of person who want to enter.
    2. must have the signature of authorized person in the letter.
  • Please provide your own transportation because Rojana transportation use for emergency only.
  • Please bring the original letter to :
    1. Rojana 1 contact Front Gate A
    2. Rojana 2 contact Front Gate 7B
    3. Rojana 3 contact Front Gate 7B * Rojana 3 can use Flatboat Only

***From 9.00-15.00

  1. Ayuthaya Office Tel.no 080 018 3781, 080 018 2174
    Contact Ms.Sabaiprae and Ms.Aree (Thai only)
  2. Bangkok Office Tel.no: 02 259 2400-3, 02 259 2923, 02 259 0494, 02 260 1248, 02 260 1288
    Contact person: Ms.Siriporn Ext. 132
    Mr.Anucha Ext. 133
 

Ref. KM199/2011

October 10, 2011


Subject: Progress Report on Flooding Situation
To: President The Stock Exchange of Thailand

Dear Sir,

As the flood crisis taking place in Ayutthaya Province is getting more and more serious, the Company has put utmost efforts to cope with such situation by strengthening and increasing the height of the existing protective dikes along the project’s area. The Company also gave warning notification to all the factories located in the industry park to build their own protective dikes for additional protection. However, the water flow and quantity influxing to the surrounding areas has been increasingly strong and overwhelming. The seriousness is getting stronger and stronger to the crisis point where the protective dikes having the wide top of three meters have been overflooded. The water has overwhelmed part of the area since October 8, 2011. The Company has undertaken repair and fixing of the dikes but it was not possible to control the whole situation. Risks are still existing if more water from other dams is again being released to the area, together with the continuing strong rain expected for next few weeks and the high sea level predicted for the middle of October. For the time being, the Company can not estimate all the losses occurring. However, such identified losses at this time are all the services income from infrastructure.

Please be informed accordingly.


Faithfully yours,
ROJANA INDUSTRIAL PARK PUBLIC CO., LTD.


Jirapongs Vinichbutr
Managing Director

 
Back

Content Download
Water Level Report as of 27 November 2011 332 KB
Water Level Report as of 26 November 2011 398 KB
Water Level Report as of 25 November 2011 426 KB
Water Level Report as of 24 November 2011 419 KB
Water Level Report as of 23 November 2011 204 KB
Water Level Report as of 22 November 2011 341 KB
Water Level Report as of 21 November 2011 362 KB
Water Level Report as of 20 November 2011 334 KB
Water Level Report as of 19 November 2011 328 KB
Water Level Report as of 18 November 2011 330 KB
Water Level Report as of 17 November 2011 339 KB
Water Level Report as of 16 November 2011 353 KB
Water Level Report as of 15 November 2011 351 KB
Water Level Report as of 14 November 2011 324 KB
Water Level Report as of 13 November 2011 351 KB
Water Level Report as of 12 November 2011 330 KB
Water Level Report as of 11 November 2011 339 KB
Water Level Report as of 10 November 2011 200 KB
Water Level Report as of 9 November 2011 205 KB
Water Level Report as of 8 November 2011 205 KB
Water Level Report as of 7 November 2011 333 KB
Water Level Report as of 6 November 2011 338 KB
Water Level Report as of 5 November 2011 336 KB
Water Level Report as of 4 November 2011 356 KB
Water Level Report as of 3 November 2011 357 KB
Water Level Report as of 2 November 2011 341 KB
Water Level Report as of 1 November 2011 331 KB
Water Level Report as of 31 October 2011 331 KB
Water Level Report as of 30 October 2011 338 KB
Water Level Report as of 29 October 2011 352 KB
Water Level Report as of 28 October 2011 335 KB
Water Level Report as of 27 October 2011 337 KB
Water Level Report as of 26 October 2011 231 KB
Water Level Report as of 25 October 2011 327 KB
Water Level Report as of 24 October 2011 324 KB
Water Level Report as of 23 October 2011 354 KB
Water Level Report as of 22 October 2011 296 KB
Water Level Report as of 21 October 2011 347 KB
Water Level Report as of 20 October 2011 327 KB
Water Level Report as of 19 October 2011 293 KB
Water Level Report as of 18 October 2011 346 KB
Water Level Report as of 17 October 2011 289 KB
Water Level Report as of 16 October 2011 329 KB
Water Level Report as of 15 October 2011 252 KB
Water Level Report as of 14 October 2011 264 KB
Back

Cleaning the road after dewatering (as of 01 Dec 11)
Cleaning the road after dewatering (as of 27 Nov 11)
Cleaning the road after dewatering (as of 25 Nov 11)
Rojana Office1 Gate A = 0.27 m. (as of 23 Nov 11)
Rojana 1 Road A = 0.27 m. (as of 23 Nov 11)
Rojana 1 Road C near Rojana Power = 0.38 m. (as of 23 Nov 11)
Rojana Office1 Gate A = 0.58 m. (as of 22 Nov 11)
Rojana 1 Road A = 0.58 m. (as of 22 Nov 11)
Rojana Office1 Gate A = 1.27 m. (as of 18 Nov 11)
Rojana 1 Road A = 1.27 m. (as of 18 Nov 11)
Rojana 1 Road C near Rojana Power = 1.38 m. (as of 18 Nov 11)
Rojana Office1 Gate A (as of 14 Nov 11)
Water Level at Rojana Office 1 Gate A = 1.80 m. (as of 14 Nov 11)
Rojana 1 Road C near Rojana Power (as of 14 Nov 11)
Water Level at Rojana 1 Road C near Rojana Power = 1.91 m. (as of 14 Nov 11)
Rojana Office1 Gate A (as of 13 Nov 11)
Water Level at Rojana Office 1 Gate A = 1.91 m. (as of 13 Nov 11)
Rojana 1 Road C near Rojana Power (as of 13 Nov 11)
Water Level at Rojana 1 Road C near Rojana Power = 2.04 m. (as of 13 Nov 11)
Rojana Office1 Gate A (as of 12 Nov 11)
Water Level at Rojana Office 1 Gate A = 1.99 m. (as of 12 Nov 11)
Rojana 1 Road C near Rojana Power (as of 12 Nov 11)
Water Level at Rojana 1 Road C near Rojana Power = 2.13 m. (as of 12 Nov 11)
Dewatering in Rojana 3 start 7 Nov 11 (as of 9 Nov 11)
Dewatering in Rojana 3 start 7 Nov 11 (as of 9 Nov 11)
Big Bag for repair Bund in Rojana 2 (as of 9/11/11)
Repairing Bund in Rojana 2 (as of 9/11/11)
Prepare Dewatering in Rojana 2 (as of 9/11/11)
Prepare Dewatering in Rojana 2 (as of 9/11/11)
Dewatering in Rojana 2 start 10/11/11 (as of 11/11/11)
Dewatering in Rojana 2 start 10/11/11 (as of 11/11/11)
Prepare Dewatering in Rojana 1 (as of 9/11/11)
Test Pump for Dewatering in Rojana 1 (as of 9/11/11)
Rojana Office1 Gate A (as of 11 Nov 11)
Water Level at Rojana Office 1 Gate A = 2.08 m. (as of 11 Nov 11)
Rojana 1 Road C near Rojana Power (as of 11 Nov 11)
Water Level at Rojana 1 Road C near Rojana Power = 2.185 m. (as of 11 Nov 11)
Rojana Office1 Gate A (as of 10 Nov 11)
Water Level at Rojana Office 1 Gate A = 2.12 m. (as of 10 Nov 11)
Rojana 1 Road C near Rojana Power (as of 10 Nov 11)
Water Level at Rojana 1 Road C near Rojana Power = 2.24 m. (as of 10 Nov 11)
Rojana Office1 Gate A (as of 9 Nov 11)
Water Level at Rojana Office 1 Gate A = 2.15 m. (as of 9 Nov 11)
Rojana 1 Road C near Rojana Power (as of 9 Nov 11)
Water Level at Rojana 1 Road C near Rojana Power = 2.27 m. (as of 9 Nov 11)
Bund near Rojana Power (as of 9 Nov 11)
Bridge near Rojana Power (as of 9 Nov 11)
Rojana Office1 Gate A (as of 8 Nov 11)
Water Level at Rojana Office 1 Gate A = 2.19 m. (as of 8 Nov 11)
Rojana 1 Road C near Rojana Power (as of 8 Nov 11)
Water Level at Rojana 1 Road C near Rojana Power = 2.31 m. (as of 8 Nov 11)
Bund near Rojana Power (as of 8 Nov 11)
Bridge near Rojana Power (as of 8 Nov 11)
Rojana Office1 Gate A (as of 7 Nov 11)
Water Level at Rojana Office 1 Gate A = 2.23 m. (as of 7 Nov 11)
Rojana 1 Road C near Rojana Power (as of 7 Nov 11)
Water Level at Rojana 1 Road C near Rojana Power = 2.35 m. (as of 7 Nov 11)
Bund near Rojana Power (as of 7 Nov 11)
Bridge near Rojana Power (as of 7 Nov 11)